By Yigit Guney, co-founder of CLEATUS and one of Executive Mosaic’s GovCon Experts.
In fiscal year 2026, 45 percent of federal solicitations on SAM.gov were amended at least once after release, according to a CLEATUS analysis of 56,036 opportunities. At defense agencies, 54.5 percent of full-and-open service solicitations changed, and one in five changed at least three times.
The analysis covers opportunities that defense and civilian agencies first released as solicitations between Oct. 1, 2025, and Sept. 30, 2026. It excludes the Defense Logistics Agency, whose high-volume parts buying follows a different pattern and whose records in our data changed mid-year.
Teams had little room to absorb those changes. The median formal solicitation gave 16 days to respond, and seven in 10 gave fewer than 30. About one in 18 solicitations changed in the final 72 hours without giving offerors any more time.
CLEATUS records every notice version for each federal opportunity it tracks. We counted an amendment as any new solicitation notice after the first, treating identical notices posted in the same minute as one. An extension is a final deadline more than 12 hours later than the original. A late change is a notice posted within 72 hours of the deadline in force at the time, and the one-in-18 figure counts only late changes after which the deadline never moved later. We collected most FY2026 notices as they posted, while most FY2025 records were loaded in bulk months later, so we do not compare the two years.

With 45 percent of federal solicitations amended after release and a median of just 16 days to respond, the Potomac Officers Club’s 2027 GovCon Executive Leadership Summit on Feb. 25 will bring C-suite leaders together to discuss capture strategy and navigating a fast-changing acquisition environment. Save your seat now!
Where Amendments Concentrate
The rate was steady through the year. From January through September 2026, between 44.5 percent and 46.5 percent of each quarter’s new solicitations were amended.
Full-and-open service solicitations, excluding construction and real-property leases, were amended 46.9 percent of the time. At defense agencies, the rate was 54.5 percent, and 19.1 percent received three or more amendments.
Agency practice varies widely:
- The Air Force amended 64.5 percent of its solicitations, the highest rate among large buyers.
- The Army and the Interior Department each amended 53.2 percent, and the Department of Veterans Affairs 51.4 percent.
- The Department of Health and Human Services amended 35.8 percent, with a median of 12.4 days to respond to formal solicitations.
- The State Department amended 31.3 percent and the Justice Department 25.9 percent.
In about one in 10 amended solicitations, the deadline, title and description stayed the same on every notice. If anything changed, it was in the attachments. Those are the amendments a team scanning notice text is most likely to miss.
At a 45 percent rate, a team with 40 open bids should expect about 18 of them to change before they close. Each one needs a named owner who re-checks the compliance matrix, the pricing assumptions and the acknowledgment log when a new notice is posted.
The Final 72 Hours
Agencies posted a notice within 72 hours of the deadline on one in six FY2026 solicitations, and most of those notices extended it. About one in 18 solicitations, 5.5 percent, changed in the final 72 hours and never got more time. For full-and-open defense service solicitations, the share was 7.2 percent, and at the Air Force, it was one in 10.
The Air Force’s Advanced Propulsion Acquisition Contract shows what that looks like. The Air Force Life Cycle Management Center posted 12 notices after the March 13 release. The due date moved once, from April 13 to April 23, and two more notices came in the final 72 hours with no extra time. Amendments like these usually answer bidder questions or fix errors in the package.
Plan the last three days around a late amendment: set an upload time ahead of the deadline, keep a writer and a reviewer free and check every amendment acknowledgment before upload. A missed acknowledgment can make an otherwise compliant proposal unacceptable.
Sixteen Days to Respond
Full-and-open service buys get short windows too. Full-and-open service solicitations gave a median of 17.1 days from release to the original deadline, and 71 percent allowed fewer than 30. Across all formal solicitations, the median was 16.2 days, and combined synopsis/solicitations gave 10.5. In the last quarter of the fiscal year, the median formal solicitation gave 14.5 days.
One in four solicitations was extended, typically by about 10 days. Fewer than 1 percent had the deadline moved earlier, so the posted date is the safe one to plan for.
With windows this short, a team that starts the compliance matrix and outline at release is already behind. Build them from the draft solicitation or the predecessor contract, and have the pricing model and teaming commitments ready before the final notice posts.
Where Software Fits
The same notice history that made this analysis possible does a different job inside CLEATUS. When a solicitation matches a team’s capture profile, CLEATUS reads the full package on arrival, including attachments and each amendment, so the team starts from a breakdown of the requirements rather than a stack of files. When an amendment posts to a tracked pursuit, an amendment workflow can summarize what changed, flag any deadline move and assign the review to its owner. Across a pipeline of dozens of pursuits, the review runs on every amendment instead of depending on someone to catch it. Before submission, package checks look for missing amendment acknowledgments.
For FY2027
The data points to three habits for the year ahead: build the proposal skeleton before release, give each amendment an owner, and keep the last 72 hours open for a late change.