NAVFAC Mid-Atlantic received three bids for the project covering Norfolk Naval Shipyard Berths 40 and 41 repairs and Dry Dock 8 modernization, the service said Thursday.
In 2018, the branch unveiled a two-decade, $21 billion investment plan to modernize its four public shipyards used to maintain nuclear aircraft carriers and submarines.
Under the task order, AECOM will help replace pile systems and caps, concrete beams, and cast-in-place concrete platforms.
The service expects work to conclude by April 2024.